The Masters House Project has this week been lucky enough to be featured in Construction News Magazine the leading journal for construction information- see below a copy of the article
Hello and welcome to the BlogSpot for the restoration of the Ledbury Master’s House. The aim of this blog is to keep those interested in the project up-to-date with the current progress on-site. We invite you to contribute and share with us your thoughts about the project progress. The blog also aims to provide you with more detail about the project and introduce you to those involved with the design & construction work for the project.
Sunday, 3 November 2013
Friday, 4 October 2013
Continuous Professional Development at the Master's House
THE MASTER’S HOUSE, LEDBURY
MEDIEVAL TIMBER FRAMING CPD
Gary Butler, a director of Butler Hegarty Architects Ltd. is an experienced academic and is recognised in the field for his expertise in timber framing. He will be directing each CPD session (approximately 1.5 hours) at The Master’s House.
These CPD sessions will be run throughout the external envelope construction phase, which predominately focuses on the repair of the medieval timber frame. These session are aimed at anyone with an interest in timber framing, that are seeking to learn more about the subject for their own professional development.
Dates:
· Tuesday 8th October
· Tuesday 22nd October
· Tuesday 19th November
· Tuesday 26th November
· Tuesday 17th December
Each CPD session will involve:
- A brief introductory talk
- A general overview of timber framing
- Site tour looking in detailed at issues
- End discussion
Each attendee will be provided with overview hand-outs, a brief questionnaire, background documents and feedback questionnaire.
CPD event and documents will cover:
Understanding the Frame
Before the work, set up of the project, frame interpretation and researching methods. What to look for when recognising framing patterns.
Dismantling the Frame
On site repairs, dismantling, repair decisions and executions
Re-framing
The process of reconstructing the building, design issues and the repair of secondary fabric/repair techniques
BOOK A PLACE
Places are limited, so please contact:
Butler Hegarty Architects
Email: mail@butlerhegartyarchitects.co.uk
Phone: 020 7263 8933
Tuesday, 3 September 2013
Update start of September
All it has been a couple of months since the last update - and we are sure people are wondering what is going on behind that hoarding! See below for some photos of the craftsmen at work!
Works to the timber frame and external masonry continue - albeit with 37 weeks to repair the frame alone there is an awful lot of work to do behind the scenes before we finally start commencing an internal fit out.
All the specialist repairs to the timber frame are being undertaken by local Herefordshire company Splitlath in conjunction with SpellerMetcalfes own staff.
Works continue well and reinstatement carpentry works to the roof are due to start the beginning of next week. The large scaffolding covering the building is not due to be removed May next year.
Tuesday, 11 June 2013
June Update
Works to repair the timber frame have now commenced - and eagle eyed locals may have noticed the construction of a timber framing yard having been built adjacent to the Old Barn in St. Katherines Car Park.
The process to repair the frame is time consuming and is being undertaken by Splitlath a specialist in restoration of historic building. It will take until Spring next year before the frame is fully repaired - which in turn will allow the roof to be replaced and allow the scaffolding to come down.
The white render that covered the building has now been removed and the brickwork behind will be refaced.
Whilst it will be difficult to see the building taking shape during that time as it is well hidden behind the hoardings and scaffolding - we will continue to update this blog regularly with photos to show off the works in progress. We have even cut some viewing holes in the hoarding so you can have a look to see the framers at work!
The process to repair the frame is time consuming and is being undertaken by Splitlath a specialist in restoration of historic building. It will take until Spring next year before the frame is fully repaired - which in turn will allow the roof to be replaced and allow the scaffolding to come down.
The white render that covered the building has now been removed and the brickwork behind will be refaced.
Whilst it will be difficult to see the building taking shape during that time as it is well hidden behind the hoardings and scaffolding - we will continue to update this blog regularly with photos to show off the works in progress. We have even cut some viewing holes in the hoarding so you can have a look to see the framers at work!
Thursday, 25 April 2013
Scaffolding Completion & Roof Removal
Despite regular snow fall throughout its erection the scaffolding was completed at the end of March as planned. The building has now been enshrouded in a large tent like canopy to keep the building weather tight while it is opened up.
Since the start of April further strip out works have commenced and the roof coverings have now been removed.
The process was undertaken under license by Natural England and was done under the watchful view of an Ecologist (no bats were found!) - will ultimately allow the removal of sections of the medieval frame for repair.
A winch has been installed as part of the scaffold structure to enable the lifting of new sections of oak.
As the building comes apart the extent and beauty of the Medieval building is really starting to be revealed. The site has recently had much interest from local groups with members of Cradley WI, the Association of Environmentally Conscious Builders and Herefordshire Technology College all visiting in the past 2 weeks.
Since the start of April further strip out works have commenced and the roof coverings have now been removed.
The process was undertaken under license by Natural England and was done under the watchful view of an Ecologist (no bats were found!) - will ultimately allow the removal of sections of the medieval frame for repair.
A winch has been installed as part of the scaffold structure to enable the lifting of new sections of oak.
As the building comes apart the extent and beauty of the Medieval building is really starting to be revealed. The site has recently had much interest from local groups with members of Cradley WI, the Association of Environmentally Conscious Builders and Herefordshire Technology College all visiting in the past 2 weeks.
Monday, 8 April 2013
Master’s House in Ledbury wins Heritage Lottery Fund support
The Master’s House in Ledbury wins
Heritage Lottery F
und support
Press Release on behalf of Herefordshire Council:
Herefordshire Council has received
a confirmed grant of £1.175 million from the Heritage Lottery Fund (HLF) for
the restoration of the Master’s House in Ledbury.
The medieval core of the building
was built in 1487 as a home for the Master of St Katherine’s hospital (now St
Katherine’s Chapel and Hall). The hospital complex also includes the Alms
Houses and the Barn; together these buildings represent a very rare surviving
example of a medieval hospital. The buildings were once set in a large estate
owned by the Dean and Chapter of Hereford.
The Master’s House has been used
for a range of uses over the years including a base for the ministry of food
during WWII, a doctor’s surgery and more recently as Herefordshire Council
office accommodation.
The project, which is also funded
by Herefordshire Council, will restore the medieval building so that it can
once again play a central role in serving the local community. The Heritage
Lottery funding will pay for the restoration of the medieval timber frame, roof
and external restoration work as well as a range of community activities
including open days during the restoration project, work placements, heritage
skills workshops, and an education programme for local schools, interpretation
boards and media to tell the story of the building through the ages.
Once completed the building will
provide a fully accessible library service for Ledbury, bookable meeting rooms
and office accommodation for Herefordshire Council staff. It will also become
the official home of the John Masefield Archive, a collection of books,
pictures, photos and artefacts related to Masefield, his poetry and his life.
The project will also provide a range of volunteering opportunities for people
of all ages. The Master’s House will continue to be the key point of contact
for Herefordshire Council customer services in Ledbury.
Councillor Roger Phillips said: “We’re delighted that the Heritage
Lottery Fund has given us this grant. The project will see long awaited
development of a new, accessible, library service for the local community and
see the future of this extraordinary building secured for the benefit of
current and future generations in Ledbury.
I would like
to take this opportunity to thank all of the local organisations and
individuals that have supported us in the development of this project and look
forward to seeing the fully restored building opening its doors to the
community in the summer of 2014”.
Monday, 18 March 2013
Scaffolding nearing Completion
Works to fully enclose the building are nearing completion - and Ledbury residents will no doubt not failed to spot the large structure that has appeared - which is clearly visible from many parts of the town centre and surrounding hills.
An early morning crane lift saw the temporary roof moved into place - after it was erected on the ground for a time taking up part of the carpark.
The temporary roof will protect the building when the roof is removed to allow the medieval timbers to be repaired and new sections of timber to be lifted into place.
An early morning crane lift saw the temporary roof moved into place - after it was erected on the ground for a time taking up part of the carpark.
The temporary roof will protect the building when the roof is removed to allow the medieval timbers to be repaired and new sections of timber to be lifted into place.
Friday, 25 January 2013
SML January 2013 Update
How quickly time flies by. Is it really already month since Christmas?! It is indeed!
So it is worthwhile giving a quick look back over the last few months and a look forward to hopefully what will be an extremely exciting year on site.
If you have been following this blog you will probably be aware we completed the
refurbishment of ‘Phase 1’ of the project back in April 2012 which allowed
Herefordshire County Council to move to their new location on the opposite side
of the Masters House.
| April 2012 - Just as the works to 'Phase 1' were being completed |
This move left the
rest of the building empty - which allowed us to strip out the building to
reveal the fabulous medieval structure that had been hidden behind centuries of
alterations.
| The Medieval structure contained within the more recent shell of the building |
A number of public Hard Hat Days were held, together with group specific visits from the local schools & Friends of the Masters House - meaning that around nearly a thousand visitors have come to site to look around whilst the works are in progress.
Since the completion of the strip out in the summer
very little actual construction work has taken place. However, we and the
design team have been busy behind the scenes working on the plans for Phase 2 -
and applications for grants to the Heritage Lottery Fund submitted. The result
of which will be known around Easter time.
Shopmobility who also occupied part of the building
have also been moved into the old Ambulance Station in Bye Street – and parking
for the users of their facilities has been created.
In preparation for a hopefully successful
application, we have undertaken works to increase the number of car parking spaces
to offset those which have now been taken up by our compound and the erection
of a large tent like scaffold which will encapsulation the building. The end
result of these alterations is that despite first impressions there is actually
the same number of spaces available for parking as there was before the works
started.
Local residents and Car Park users will doubt have noticed that despite rather snowy conditions the scaffold erection has commenced this week and
will take place over the next couple of months. It will fully encapsulate the
building and allow for the removal of the roof whilst protecting the precious
timbers from the weather.
| Scaffolding being erected looking from the direction of the 'Alms Houses' |
| Access Scaffolding on the South Side of the Building |
As ever during our time on site we will endeavor to
ensure that our employees and subcontractors perform in the most courteous
manner possible with the minimum of disruption for you. A large percentage of the construction team
are Ledbury residents and, as such, understand the ongoing concerns over the
impact that these works may have on the surrounding area, the public and local businesses.
The site is registered under the Considerate
Constructors Scheme; an independently assessed scheme which monitors our
activities in a number of key areas designed to both minimise the impact of our
works, but also our contribution to the local area. For more information on the
scheme visit www.ccscheme.org.uk.
If, at any time, you wish to raise query or concern
regarding the works, please contact either our resident Site Manager Ed
Mandrell on 07976763579, or visiting Contracts Manager Pat Gorin on 07817240153.
Thursday, 3 January 2013
The Master’s House – Update January 2013
The end of 2012 saw a flurry
of activity associated with the Master’s House.
At the beginning of December the Project Team submitted its application
to the Heritage Lottery Fund for a grant of over a £1 million to help secure
the future of the building. The Grant
application is for monies towards both the restoration works and for a range of heritage activities and interpretation telling the story of the building as part of a medieval hospital complex.
At the end of December, Listed
Building Consent was granted to Herefordshire Council for the proposed works at
the Master’s House. Early in the New Year the Project
Team will be submitting another bid for funding, this time to English
Heritage, for help with the costs of refurbishment.
Wednesday, 19 December 2012
Changes to the St Katherine’s Car Park, Ledbury
Local residents and Visitors may
have noticed some remarking of the car parking spaces at St Katherine’s. The work has been done in preparation for the
erection of a large scaffolding that will be required as part of the refurbishment
of the Master’s House.
The most significant change has
been the replacing the Car Parking spaces between the Master’s House and the
Alms-houses with three spaces for Disabled Parking Spaces. This loss of spaces has been compensated for
by creating more spaces elsewhere within the Car Park. The work was programmed to minimise
disruption over Christmas and the New Year. The scaffolding is due to be erected in February but preparatory works
will commence early in the New Year to prepare the site.
For more details please contact Andy Tector at Herefordshire Council on 01432 261989 or email aet@herefordshire.gov.uk
Thursday, 29 November 2012
This week at the Masters House
Last weekend saw a very successful Hard Hat Day which despite dismal weather conditions attracted over 250 people to guided by HCC staff & members of the 'Friends of the Masters House' and give their views on the future of the landscaping around St. Katherines.
Last Friday's edition of the Ledbury Reporter also featured a very positive full page write up -follow this link to read the online edition. http://www.ledburyreporter.co.uk/news/10071428.Master_s_House_work_under_way/
Behind the scenes work continues on the design, and as per the Reporter article the team is working on hopefully a successful Heritage Lottery Bid which will propel Phase 2 of the project into action in the New Year.
On site - eagle eyed people will have spotted a decontamination unit in the carpark as asbestos that was concealed below the floor is removed following the departure of shopmobility from that wing of the building.
Tuesday, 20 November 2012
Hard Hat Tours of the Master's House - 24.11.12
Hard Hat Guided Tours of the Medieval Master's House
24th November 2012 from 10am - 2pm
Come and see the Master's House and take the opportunity to comment on the proposed landscape design for the St
Katherine’s site . . . .
Come and see the recently exposed medieval part of the building and see the plans for the exciting redevelopment of this historically important building of Ledbury.
We will also be seeking your comments on
the proposed landscape design for the area around the Master’s House, which will be on display at the Master's House.
For further information
please contact Mick Ligema at Herefordshire Council on 01432 260631 or email: mligema@herefordshire.gov.uk
Monday, 19 November 2012
St. Katherines Car Parking Works
Works were completed over the weekend to rearrange the white lining in preparation for the later phase of works to the Masters House.
The layout as it stands in front of the Masters House nearest the High Street may seem a little strange until the likely extent of the scaffolding is viewed. The spaces have been rotated to allow for the scaffolding to encroach from the front of the building whilst maintaining access to St. Katherines Hall.
Additional spaces have been created in front of the HCC offices and in the corner of the carpark where the recycling bins used to be located. Parking for motorcycles has also been refreshed.
Shopmobility
Ledbury Shopmobility ran by Community Voluntary Action Ledbury & District has now moved to the old Ambulance Station in Bye Street. There are 3 new disabled bays outside the Ambulance Station for users of the scheme.
For more information contact them on 01531 635339 or visit their Facebook page.
http://www.facebook.com/#!/CommunityVoluntaryActionLedbury?fref=ts


For more information contact them on 01531 635339 or visit their Facebook page.
http://www.facebook.com/#!/CommunityVoluntaryActionLedbury?fref=ts


Wednesday, 17 October 2012
St. Katherines Car Park Works
As part of the precommencement works for the main Phase 2 of the project due to commence in 2013 we will undertaking carpark alterations commencing Tuesday 30th October which will run for 3 weeks.
There may be minor disruption to the carpark but this should be minimal and should not affect the normal usage of the carpark.
The Carpark will be closed on Sunday 18th November (weather permitting) for Line Marking.
The works include the removal of existing flower beds to provide 5nr additional standard carparking spaces, 3 extra disabled spaces, the formation of an area of a site compound and the installation of an upgraded telephone line system.
3 further disabled spaces have also been already formed at the former ambulance station users of the Shopmobility scheme.
These alterations are necessary to offset the carpark spaces that will taken up by the erection of the scaffolding on the North & East elevations once Phase 2 starts.
There may be minor disruption to the carpark but this should be minimal and should not affect the normal usage of the carpark.
The Carpark will be closed on Sunday 18th November (weather permitting) for Line Marking.
The works include the removal of existing flower beds to provide 5nr additional standard carparking spaces, 3 extra disabled spaces, the formation of an area of a site compound and the installation of an upgraded telephone line system.
3 further disabled spaces have also been already formed at the former ambulance station users of the Shopmobility scheme.
These alterations are necessary to offset the carpark spaces that will taken up by the erection of the scaffolding on the North & East elevations once Phase 2 starts.